Skip to main content

Construct Materials Lab

Illinois Department of Transportation

CDB Project No. 630-442-057

February 13, 2024

At their regularly scheduled meeting on February 13, 2024 the Capital Development Board concurred with the Design-Build Selection Commitee's recommendation to award the contract to The Korte Company.

Phase II RFI & Responses            Published 11/09/2023

Phase II RFI & Responses            Published 11/07/2023

Phase II RFI & Responses            Published 10/04/2023 (Revised 11/07/2023)

Phase II RFI & Responses            Published 9/27/2023 (Revised 11/07/2023)

Phase II RFI & Responses            Published 8/31/2023  

The following teams were shortlisted by the committee on July 19, 2023 to participate in Phase II:

Core Construction Services of Illinois, Inc.
Korte Construction Company dba The Korte Company
Walsh Construction Company II, LLC

PHASE I Submittals

Submittals were received from the following firms on June 9, 2023:

Core Construction Services of Illinois, Inc.
Korte Construction Company dba The Korte Company
River City Construction, LLC
Walsh Construction Company II, LLC

NOTICE OF REQUEST FOR PROPOSAL published 5/12/2023

The Capital Development Board ("CDB") issues a Request for Proposal (RFP) for the following Design-Build project:

CDB Project No. 630-442-057
Construct Materials Lab – Illinois Department of Transportation
Springfield, Sangamon County, Illinois
Published Construction Project Budget - $63,400,098.00

Pre-Submittal Meeting

A pre-submittal meeting was held at 10:00am on May 19, 2023 in the auditorium of the Hanley Administration Building at 2300 S. Dirksen Parkway, Springfield, Illinois.

Pre-Submittal Meeting Agenda

Pre-Submittal Meeting Attendance Record

Phase I RFI & Responses               Published 6/5/2023    

Specifications and Forms

 

Amendment 3 Published 11/7/2023
Bridging Documents II-5-Basis of Design Laboratory Published 11/7/2023
II-9 Basis of Design-Electrical_Lighting Published 11/07/2023
630-442-057 CDB IDOT OPR Published 11/7/2023
630-442-013 d0693 Published 11/7/2023
630-442-017 d0693 Published 11/7/2023
D0693 Asbestos Inspection Report Published 11/7/2023
Appendix III.3 Date Room Sheet 1.1 1-2.95 Published 11/7/2023
IDOT Equipment Matrix Published 11/7/2023
Appendix III.6 Contaminated Soils Published 11/7/2023
IDOT Borrow Materials Memo Published 11/7/2023
Borrow Materials Stockpile Location Graphic Published 11/7/2023
Amendment 2 Published 7/13/2023
Project Labor Agreement Published 7/13/2023
Amendent 1 Published 06/5/2023​

​Request for Proposal (RFP)

​Published 05/12/2023​

​Design-Build Proposal Transmittal Form (DB-PTF)

Design-Build Pricing Schedule (DBPS)

​Standard Business Terms and Conditions and Standard Certifications

Financial Disclosures and Conflicts of Interest

DB Entity Qualifications Form and Instructions (DBQ)

​Reference Questionnaire

MBE/WBE/VBE/PBE Phase I Utilization Plan

​MBE/WBE/VBE/PBE Phase II Utilization Plan

PC-2 Workforce Projection

Bid Bond

Selection Criteria Weighting

​Supplement to SD-DB

Bridging Document - Project Manual Part I & II

Appendix III.1 Owners Project Requirements

Appendix III.2 Program Area Tables

Appendix III.3 Data Room Sheets

Appendix III.4 Lab Equipment Matrices

 

Appendix III.5 SD-DB

 

Appendix IV.1 Geotechnical Investigation

 

Appendix IV.2 Existing Site Survey

 

Lab Equipment Cut Sheets

 

Appendix V.1 Conceptual Drawings

 

Appendix V.2 LEED

 

NOTICE OF INTENT TO ADVERTISE published 4/25/2023

The Capital Development Board ("CDB") intends to issue (on or after May 9, 2023) a Request for Proposal (RFP) for the following Design-Build project:

CDB Project No. 630-442-057
Construct Materials Lab – Illinois Department of Transportation
Springfield, Sangamon County, Illinois
Published Construction Project Budget - $63,400,098.00

Footer